Project schedule

We'll update this page whenever we receive project schedules from the contractor.

Lane closure schedule


Check for any scheduled lane closures or other Main Street roadwork on the project's Traffic Alerts page.
Timeline (all dates are in 2017) What's happening
Mid Oct. - mid Nov. Single block closure, no vehicular traffic between 101st and 102nd Ave NE
Aug. 14 - Sept. 15 Single block closure, no vehicular traffic between Bothell Way NE and 101st Ave NE
Apr. Construction begins
Mar. 28 Groundbreaking celebration
Feb. 8 Bid opening
Jan. - Mar. Franchise utility relocation
​(Puget Sound Energy and Frontier)
Jan. 11 Meeting with Main St business owners to prepare for construction
Jan. 2017 Finalize the design
Sign up for construction updates to receive periodic news about the project! http://www.bothellwa.gov/list.aspx