Crossroads Phase I

Bothell City Council awarded the first phase of Bothell Crossroads to Titan Earthwork, LLC on February 23, 2010. The work involved demolishing fourteen (14) buildings located in the area of the future SR 522 alignment, and included abatement of hazardous materials and utility disconnections. As part of these activities, efforts were made to recycle, reuse, or salvage existing materials on site.

The project commenced on March 29, 2010 and was physically completed on May 21, 2010 (five weeks ahead schedule) for a total cost of $339,224.