Pavement Overlay 2015


The project provided an asphalt pavement overlay of three streets:
  • 4th Ave West between 228th St SW and 216th St S
  • 9th Ave SE between 228th St SE and SR 524
  • 240th St SE at 34th Ave SE

The work included:

  • Milling in selected areas
  • Subgrade replacement in highly distressed areas
  • Placement of asphalt pavement
  • Upgrades to curb ramps impacted by the asphalt pavement repair
  • Storm drainage work
  • New lane striping


The estimated cost for this project was $1,100,000.


Work finished up in late April 2016.