Penn Park Reservoir Replacement

News and project updates


January 17, 2017 
 
The new water tank is in place, but not yet operational. Underground utility work is finished and the wall is constructed. Electrical work might wrap up by the end of this month.
  
Once the tank's interior is painted, the contractor will start filling it with water. We anticipate the tank may be functional by mid February.

Painting the exterior of the tank is weather dependent. Penn Park remains closed to users until further notice.

Project description


As part of the City's adopted Water Comprehensive Plan, we replaced the potable water storage tank located in Penn Park to increase its storage capacity.  The new tank is in the same location as the existing tank, but has a larger footprint.  The estimated construction cost is $2.7M.

The former water tank served the area since 1960.

Public impacts


Penn Park is closed to users during construction. In the mean time, why not visit one of Bothell's other parks?

Schedule


Construction began in late March and should wrap up by spring 2017. 

Now you see it...

Now you don't.

Penn Park Existing Tank built in 1960
Penn Park Former Location
Penn Park Aerial