Status
The City has surveyed the project and collected preliminary information. The City's consultant is developing the design and acquiring the necessary permits.
The design is about 90% complete.
Design schedule
- Preliminary Design: March 2015
- Public Meeting - April 2015
- Public Meeting - December 10, 2015
- Public Hearing - July 19, 2016
- Public Hearing (SEPA appeal) - August 18, 2016
- 90% Design - Fall 2016
- 100% Design - Fall 2018
- Advertise for Construction Contract (estimated) - January 2019
Community benefits
Transit speed and reliability would be improved with the installation of BAT lanes where none currently exist. This would support the vision of downtown Bothell as a transit-friendly urban core. Installation of a sidewalk on the north side of the highway would allow the neighborhoods to access intersections along SR 522 and cross the regional trail system. This would promote pedestrian and bicycle usage.