Bothell Connector - 39th Avenue SE Extension


The project proposed to construct a 3-lane arterial roadway from 240th Street SE to north of 228th Street SE where there is currently a gap in the existing north-south arterial. Other project elements would have included bicycle lanes, planting strips, sidewalks and reconfigured and signalized intersections. The City of Bothell and Snohomish County were partners in this project.


  • Public Draft EIS: June 1, 2004
  • Draft EIS Public Meeting: June 15, 2004
  • Comment Period Ends: July 15, 2004
  • Public Meeting: February 10, 2005
  • Bothell City Council Adopts Preferred Alternative: April 18, 2005
  • Publish Final EIS: November 2, 2006
  • Notice of Action: November 13, 2006
  • Complete 60% Design/Right of Way Plan: Summer 2008
  • Final Design/Permitting/Right of way Acquisition: Unable to proceed due to lack of funding
  • Construction: Project was removed from the Transportation Improvement Program by Council vote on November 18, 2014