Bothell Connector - 39th Avenue SE Extension

Description


The project proposed to construct a 3-lane arterial roadway from 240th Street SE to north of 228th Street SE where there is currently a gap in the existing north-south arterial. Other project elements would have included bicycle lanes, planting strips, sidewalks and reconfigured and signalized intersections. The City of Bothell and Snohomish County were partners in this project.

Schedule


  • Public Draft EIS: June 1, 2004
  • Draft EIS Public Meeting: June 15, 2004
  • Comment Period Ends: July 15, 2004
  • Public Meeting: February 10, 2005
  • Bothell City Council Adopts Preferred Alternative: April 18, 2005
  • Publish Final EIS: November 2, 2006
  • Notice of Action: November 13, 2006
  • Complete 60% Design/Right of Way Plan: Summer 2008
  • Final Design/Permitting/Right of way Acquisition: Unable to proceed due to lack of funding
  • Construction: Project was removed from the Transportation Improvement Program by Council vote on November 18, 2014