Pavement Overlay 2016

  1. News & project updates
  2. What's happening now

Weather pushes work into November

October 18, 2016 

CEMEX, the City's contractor, is paving several streets in the North Creek Business Park area. The weather has delayed striping and marking the pavement. This last bit of work will resume and finish up in early November.
  1. Project description
  2. Elements

Project description

As part of Bothell’s annual Pavement Preservation Program, the City identified three street segments that could benefit from an asphalt overlay and repairs: 
  • 120th Ave NE from NE 195th St to 132nd Ave NE
  • North Creek Parkway and North Creek Parkway N
  • Settlement area on 120th Ave NE / 39th Ave SE, just north of North Creek Parkway N

Public impacts

During construction, there will be temporary lane closures and lane shifts for paving work.  These closures will generally occur between 9 am and 3 pm, but could occasionally be longer.  See traffic alerts for this project.
City staff has contacted local business and property owners along these road segments to talk about the traffic impacts.